Steps in Commissioning a 1250 kW or Larger Generator Set

Generator Infographic

Download PDF

The steps in commissioning a 1250 kW or larger generator set:

• GPS Quote

• Customer PO

• GPS Submittal

• Customer Submittal Approval

• Production Begins

• Generator Manufacturing

• Enclosure Manufacturing

• Generator Completion

• Generator Ships to Enclosure Manufacturer

• Assemble Completed Generator

• Genset Completes at Enclosure Manufacturer

• Enclosed Genset Delivered to Site

• Offload Genset at Customer’s Facility

• Customer Installation of Genset

• Contractor Completes Generator Pre-Startup Checklist

• Generator Technician Performs Start-up

• Genset Warranty is Initiated

• Customers Commissioning Agent Instructs GPS Technician Commissioning Plan

• Genset is Commissioned

• Site is Operational

• Generator is put into Service Plan

Global Power Supply supports and installs multiple systems nationwide through our Project Management Programs and our certified Project Management Professionals (PMP). From technical, material and engineering resources to project management and logistics services GPS can provide a single source solution for all your critical power needs.